A refused application can sink a scheme's viability overnight. Months of due diligence, a purchase under option, a build programme pencilled in - all of it rests on a decision made by a committee or a case officer who may never have visited the site. Getting planning permission right is where development risk concentrates, and it's rarely as simple as filling in a form.
Most guides to planning permission are written for homeowners extending a kitchen or converting a loft. This one isn't. Here, we're covering how the planning permission system actually works, what it costs, how long it takes, and - because this is the part homeowner guides skip entirely - how to judge your chances of approval before you commit to a site.
Planning permission is formal consent from the local planning authority (LPA) to carry out development, which includes building work, engineering operations, and material changes of use to land or buildings. The legal basis sits in the Town and Country Planning Act 1990 (itself building on the original 1947 Act), which created the framework requiring consent for development in England.
Not everything you do to a site counts as "development" in the legal sense, and not all development needs an application. Full guidance on when permission is and isn't required is set out on GOV.UK. The test runs in two stages:
If your proposal clears both hurdles, you don't need to apply. If it doesn't, you're into the formal application process.
Not every application is the same, and picking the wrong route wastes time and money. Here's what developers need to know:
For developers working on commercial schemes, most applications fall under full or outline permission, with reserved matters following where outline consent has already been secured. Commercial planning permission doesn't differ procedurally from residential permission, but the supporting evidence base - transport assessments, commercial viability appraisals, and environmental information - tends to be more substantial.
The process is broadly consistent across England, though timescales and local requirements vary by authority. GOV.UK sets out the formal application steps in full; here's how it runs in practice:
The process is broadly consistent across England, though timescales and local requirements vary by authority. GOV.UK sets out the formal application steps in full; here's how it runs in practice:
At each stage, the developer's job is to reduce uncertainty for the case officer. That means engaging early, providing a complete and well-evidenced application, and responding quickly to consultation feedback rather than letting objections sit unanswered.
Application fees are set nationally but reviewed periodically, so it's worth checking the current schedule using the Planning Portal's fee calculator rather than relying on a figure that may already be out of date. Community Infrastructure Levy and Section 106 contributions sit alongside application fees once a scheme is approved; our guide to CIL and planning obligations covers how these are calculated and when they apply.
On timescales, the 8-week and 13-week statutory periods are targets, not guarantees. Delays commonly come from incomplete submissions at validation, requests for further information during consultation, or committee scheduling for applications that can't be decided under delegated powers. Our data deep dive on planning determination periods looks at how actual council performance compares to the official statistics, and why building contingency into your programme is sensible, particularly for major schemes.
Conditions attached to a permission are just as important as the decision itself. Some conditions must be discharged before development begins (pre-commencement conditions); others apply throughout construction or before occupation. It's also worth knowing the 3-year commencement rule: a full planning permission normally lapses if development hasn't started (a "material start", which has its own legal definition) within three years of the decision date. Missing that window means reapplying from scratch.
This is the part almost no planning permission guide covers, because almost none of them are written for developers weighing up whether to buy a site in the first place.
Before you commit capital, three things tell you far more than the LPA's published policy alone:
Pulling all of this together manually, site by site, is slow. It usually means separate searches across the LPA's planning portal, the Planning Inspectorate's appeal decisions, and the local plan documents, before you've even started assessing the site itself.
LandInsight brings planning history, constraints, and policy designations together on one map, so you can judge a site's approval odds before you commit capital rather than after. It's built for exactly this stage of the process: the point where you need a fast, evidence-based read on a site's potential, not another spreadsheet of unlinked data.
How long does planning permission take? The statutory targets are 8 weeks for minor applications and 13 weeks for major developments, though actual timescales often run longer. See our data deep dive on planning determination periods for a detailed breakdown of how actual council performance compares.
How much does planning permission cost? Fees depend on the type and scale of application and are set nationally, though the schedule is reviewed periodically. Use the Planning Portal's fee calculator for the current figure, and see our guide to CIL and planning obligations for the costs that follow approval.
What is the difference between full and outline permission? Full permission covers the complete design in one application, while outline permission establishes the principle of development first, with the detailed design settled later through a reserved matters application.
Can you start work before permission is granted? No. Starting work without the necessary consent risks enforcement action, and any development carried out before permission is granted isn't protected, even if the application is later approved. Where work has already started or finished without consent, a retrospective application may be an option, though LPAs assess these on the same merits as any other application, with no guarantee of approval.
What happens if planning permission is refused? You can appeal the decision to the Planning Inspectorate, amend and resubmit the application, or reconsider the scheme's design in light of the refusal reasons. Our guide to how long planning appeals take covers what to expect from the process.
Planning permission is where development risk lives. The developers who win aren't necessarily the ones with the best schemes on paper; they're the ones who can read a site's chances before they buy. LandInsight brings planning history, constraints, and policy onto one map, so you can judge a scheme's odds from day one.